We believe in transparency. Below are letters sent and received by the Fix Flat Rock Steering Committee.

📧 Have a suggestion? Email us at fixflatrock@enviro.org.au

📥 RECEIVED – From: Elizabeth Landman from GRC
📅 October 27, 2026
⏳ Pending Response

latest from GRC on flat rock for Fix Flat Rock community

Summary: What I heard in our conversation is that you would like Council to;<br><br>

As a first priority take lead and fund all approvals required to get a section of beach replenished with sand.<br>
Second priority would be the 7m x 2m rock groyne designed, approved and build by Council, so that it slowdowns the tidal movements and future sand replenishment would not be required or at least minimised.<br><br>
Consider upgrade of the area including the playground and shading for locals to enjoy this area and attract more tourist to this area as it was back in its high day when the boat club was active and it becomes a real meeting place for community again.

📄 Click to view full letter
FW: latest from GRC on flat rock for Fix Flat Rock community - sunirmalya@gmail.com - Gmail
background image

sunirmalya symons

FW: latest from GRC on flat rock for Fix Flat Rock community

1 message

Elizabeth Landman 

26 October 2026 at 14:19

To: "sunirmalya@gmail.com"

Dear Mr Symons

 

Thank you for taking my call today.

As discussed, please find my email and contact detail if you want to follow-up on progress.

 

What I heard in our conversation is that you would like Council to;

1. 

As a first priority take lead and fund all approvals required to get a section of beach replenished with sand.

2. 

Second priority would be the 7m x 2m rock groyne designed, approved and build by Council, so that it
slowdowns the tidal movements and future sand replenishment would not be required or at least
minimised.

3. 

Consider upgrade of the area including the playground and shading for locals to enjoy this area and attract
more tourist to this area as it was back in its high day when the boat club was active and it becomes a real
meeting place for community again.

 

As none of this is funded, I will be working with my colleagues to see how we would progress this request and be
in contact as discussed.

 

Kind regards

Elize

 

Elizabeth Landman

Manager Environment and Conservation

Assets and Environment

PO Box 29 Gladstone Qld 4680

P

  

(07) 4970 0700  |  

M

  0472 524 269

W

  

www.gladstone.qld.gov.au

10/27/26, 6:58 PM

Gmail - FW: latest from GRC on flat rock for Fix Flat Rock community

https://mail.google.com/mail/u/0/#all/CllgCHrjmdHLklngplmXBxdWlzvJjcSVCcFLNlRCgDKcqHNccHhkpjTTPkdQWHrqkGXhDntMZVB

1/3

background image

Gladstone Regional Council would like to acknowledge the traditional custodians of this land, the Bailai, the Gurang, the Gooreng Gooreng
and the Taribelang Bunda people. We pay respect to their Elders past, present and emerging. Gladstone Regional Council is committed to
cultivating a culture of inclusion and connectedness, acknowledging that our communities are richer when diversity is embraced.

 

From:

 sunirmalya symons <

sunirmalya@gmail.com

>

Sent:

 Wednesday, 16 September 2026 2:09 PM

To:

 Stephen Bennett <

Burnett@parliament.qld.gov.au

>; Natalia Muszkat <

Natalia.Muszkat@gladstone.

qld.gov.au

>

Subject:

 Re: latest from GRC on flat rock for Fix Flat Rock community

 

 

CAUTION:

 This email originated from outside of Council. Do not click links or open attachments unless you

recognise the sender and know the content is safe.

FYI please can keep in the loop by checking 

https://fixflatrock.dreamhosters.com/correspondence.php

 

So i wrote to the Mayor and Deputy Mayor with this  

Hi Matt and Natalia,

I hope you’re both doing well.

I’m reaching out regarding the ongoing coastal erosion at the Flat Rock Picnic Area in Baffle Creek. We recently
received the official pre-lodgement advice from the State Assessment and Referral Agency (SARA) regarding our
proposed beach replenishment and 7m x 2m rock groyne, and I wanted to bring you into the loop on where things
stand.

SARA’s response gives us a clear regulatory roadmap, but it also highlights a critical structural point: because the site
sits below the Highest Astronomical Tide (HAT) within the declared Baffle Creek Fish Habitat Area (FHA Management
B), State agencies rarely grant approvals for permanent works or tenure to private individuals or community groups.
SARA explicitly noted that Gladstone Regional Council (GRC) would naturally be the appropriate lead applicant and
managing entity for works protecting this road reserve and public infrastructure.

To ensure this project succeeds without getting bogged down in state bureaucracy, we’d like to work directly with
Council to streamline the path forward. Specifically:

1. 

Council Proponent/Sponsorship:

 Exploring whether GRC can step in as the primary applicant or co-

proponent for the development application and landowner’s consent process through DNRMMRRD
(Department of Natural Resources and Mines, Manufacturing and Regional and Rural Development ).

2. 

Refining Application Scope 

There was some confusion about the scope of the proposal to focus strictly on

the essential erosion control (the rock groyne and soft replenishment).

3. 

Inter-Agency Alignment:

 Arranging the recommended pre-lodgement meeting with DNRMMRRD

(

LASST3@nrmmrrd.qld.gov.au

) and securing the Resource Allocation Authority (RAA) under the 

Fisheries Act

.

10/27/26, 6:58 PM

Gmail - FW: latest from GRC on flat rock for Fix Flat Rock community

https://mail.google.com/mail/u/0/#all/CllgCHrjmdHLklngplmXBxdWlzvJjcSVCcFLNlRCgDKcqHNccHhkpjTTPkdQWHrqkGXhDntMZVB

2/3

background image

Flat Rock remains a vital asset for our local community and visitors alike, and we want to ensure we protect the area
properly. With respect, Baffle Creek does seem to miss out repeatedly. Given that Tony Kleins master plan of 2015
was the last visionary statement for the area and none of it was implemented we are keen for something to be done.

Could we catch up briefly or set aside 15 minutes soon to discuss how Council and our committee can best align on
this?

Warm regards,

Sunirmalya Symons

Fix Flat Rock Steering Committee

 

 

Disclaimer:

 This email and any attachments may contain confidential or privileged information. You must not use or disclose this information,

other than for the purposes for which it was supplied. The privilege or confidentiality attached to this email and attachments is not waived by
reason of mistaken delivery to you. If for whatever reason this email is received by someone other than the intended recipient, you are
requested to notify the sender promptly by telephone, email or facsimile and destroy and delete all copies of the original message. Personal
information will only be disclosed to a third party with your written authorisation or as required by law – Refer to Council’s website for more
information relating to 

Privacy 

or 

Right to Information.

10/27/26, 6:58 PM

Gmail - FW: latest from GRC on flat rock for Fix Flat Rock community

https://mail.google.com/mail/u/0/#all/CllgCHrjmdHLklngplmXBxdWlzvJjcSVCcFLNlRCgDKcqHNccHhkpjTTPkdQWHrqkGXhDntMZVB

3/3

📥 RECEIVED – From: Deputy
📅 September 15, 2026
✓ Responded

reply from Natalia

📄 Click to view full letter
Suni, I am following this up now with the Mayor and CEO. Will be in touch asap.

Natalia

Gladstone Regional Council
Natalia Muszkat
Deputy Mayor
Gladstone Regional Council

PO Box 29 Gladstone Qld 4680
P (07) 4970 0700 | M 0436 646 201
W www.gladstone.qld.gov.au
📤 SENT – To: Mayor Matt Burnett and Deputy Mayor Natalia Muszkat
📅 September 15, 2026

Update & Next Steps: Flat Rock Erosion Mitigation (SARA Pre-Lodgement Advice)

📄 Click to view full letter
Hi Matt and Natalia,

I hope you’re both doing well.

I’m reaching out regarding the ongoing coastal erosion at the Flat Rock Picnic Area in Baffle Creek. We recently received the official pre-lodgement advice from the State Assessment and Referral Agency (SARA) regarding our proposed beach replenishment and 7m x 2m rock groyne, and I wanted to bring you into the loop on where things stand.

SARA’s response gives us a clear regulatory roadmap, but it also highlights a critical structural point: because the site sits below the Highest Astronomical Tide (HAT) within the declared Baffle Creek Fish Habitat Area (FHA Management B), State agencies rarely grant approvals for permanent works or tenure to private individuals or community groups. SARA explicitly noted that Gladstone Regional Council (GRC) would naturally be the appropriate lead applicant and managing entity for works protecting this road reserve and public infrastructure.

To ensure this project succeeds without getting bogged down in state bureaucracy, we’d like to work directly with Council to streamline the path forward.

Specifically: 1. Council Proponent/Sponsorship: Exploring whether GRC can step in as the primary applicant or co-proponent for the development application and landowner’s consent process through DNRMMRRD (Department of Natural Resources and Mines, Manufacturing and Regional and Rural Development ).
2. Refining Application Scope There was some confusion about the scope of the proposal to focus strictly on the essential erosion control (the rock groyne and soft replenishment).
3. Inter-Agency Alignment: Arranging the recommended pre-lodgement meeting with DNRMMRRD (LASST3@nrmmrrd.qld.gov.au) and securing the Resource Allocation Authority (RAA) under the Fisheries Act.

Flat Rock remains a vital asset for our local community and visitors alike, and we want to ensure we protect the area properly. With respect, Baffle Creek does seem to miss out repeatedly. Given that Tony Kleins master plan of 2015 was the last visionary statement for the area and none of it was implemented we are keen for something to be done. Could we catch up briefly or set aside 15 minutes soon to discuss how Council and our committee can best align on this?

Warm regards,
Sunirmalya Symons
Fix Flat Rock Steering Committee
📥 RECEIVED – From: rockhamptonsara@dsdip.qld.gov.au
📅 August 31, 2026
⏳ Pending Response

2606-53184 SPL application correspondence

Summary: why we're screwed

📄 Click to view full letter
TEMPLATE - Pre-lodgement Advice V 1-1
PA6-L
State Assessment and Referral Agency
Page 1 of 8
SARA reference:
2606-53184 SPL
1 September 2026
Sunirmalya Symons
sunirmalya@gmail.com
Dear Sunirmalya
SARA Pre-lodgement advice – Flat Rock Picnic Area, Baffle
Creek
I
refer
to
your
pre-lodgement
request
received
on
25
June
2026
in
which
you
sought
pre-lodgement
advice from the State Assessment and Referral Agency (SARA) regarding the proposed development at
the above address.
This notice provides advice on aspects of the proposal that are of relevance to SARA that is based on the
documentation uploaded into MyDAS2 on 25 June 2026.
Development details
Summary of proposal:
The proposed development involves beach replenishment works (a 'soft'
engineering approach to erosion control) and the construction of a 7m x
2m rock groyne at the Flat Rock Picnic Area, Baffle Creek. The works
are
required
to
address
ongoing
coastal
erosion
that
threatens
public
infrastructure,
including
the
public
boat
ramp
and
picnic
area.
Beach
replenishment is proposed as part of an integrated erosion management
solution,
as
it
allows
the
beach
to
continue
to
behave
naturally
while
providing protection to coastal structures.
Description:
Development Permit for Operational work (beach replenishment works)
SARA role:
Assessment manager or referral agency (to be determined)
SARA jurisdiction under the
Planning Regulation 2017:
Operational work in a declared Fish Habitat Area (FHA)
Operational
work
that
is
tidal
works
or
work
in
a
coastal
management district
Operational
work
involving
removal,
destruction
or
damage
of
marine plants (potential SARA jurisdiction)
Operational work for high impact earthworks in a wetland protection
area (potential SARA jurisdiction)
Operational
work
that
is
tidal
works
or
work
in
a
coastal
management district in tidal waters (potential SARA jurisdiction)
Note: If confirmation of SARA's jurisdiction is sought, further information
should
be
provided
to
clarify
whether
the
proposal
requires
a
development application to Gladstone Regional Council as assessment
manager. Following confirmation of the applicable assessment pathway,
2606-52184 SPL
State Assessment and Referral Agency
Page 2 of 8
SARA can determine whether it has jurisdiction as a referral agency or
assessment manager and applicable provisions.
Street address:
Flat Rock Picnic Area, Baffle Creek
Real property description:
Formally described as unallocated state land adjoining Lot 3 SP16452
(GPS coordinates -24.5113, 152.0217)
Pre-lodgement advice
SARA provides the following pre-lodgement advice:
Table 1: SARA advice in response to your request
Table 2: Additional SARA advice
Table 3: Additional advice outside the jurisdiction of SARA.
Table 1: SARA advice in response to your request
Advice requested:
For the DA I am only able to provide adjacent lot not the actual beach front,
can you advise how to proceed. I do have approval from the adjacent land holder and GRC
1.
Owner’s consent to lodge a development application
It is acknowledged you seek advice regarding owner's consent for proposed operational work on
State
land.
It
is
understood
the
proposed
construction
of
a
rock
groyne
(7m
x
2m)
and
associated beach replenishment (200m²) is below highest astronomical tide (HAT).
The
Department
of
Natural
Resources
and
Mines,
Manufacturing
and
Regional
and
Rural
Development (DNRMMRRD) recommends that you engage directly with DNRMMRRD regarding
owner's consent and tenure requirements associated with the proposed works. Where owner's
consent under the
Planning Act 2016
is required for works on premises below high-water mark
and outside a canal, an application for owner's consent will need to be made to DNRMMRRD.
To
assist
DNRMMRRD
in
determining
any
owner's
consent
and
tenure
requirements,
the
application should include:
a copy of the development application and attachments proposed to be lodged with the
assessment manager
a
survey
(either
a
full
survey/resurvey
or
an
identification
survey)
completed
to
a
professional
standard
in
accordance
with
Part
7
of
the
Surveying
and
Mapping
Infrastructure Act 2003 of the ambulatory boundaries of the road/esplanade (Flat Rock
Road) adjoining the proposed work area
correspondence from Gladstone Regional Council (as road manager) providing its views
with respect to any use or impacts of the proposed works on Flat Rock Road.
Application forms and information on lodging an application for owner's consent can be found on
DNRMMRRD's website at:
Owner's consent for a development application
.
Prior
to
lodging
an
application
for
owner's
consent,
you
are
encourages
to
arrange
a
pre-
lodgement
meeting
directly
with
DNRMMRRD.
Early
engagement
may
assist
in
minimising
delays and ensuring there is an accurate understanding of the proposed development and its
impacts.
Please contact the Rockhampton Land Administration and Tenure Solutions team via email at
LASST3@nrmmrrd.qld.gov.au
to arrange a meeting.
In addition, it is recommended that you discuss the proposal with Gladstone Regional Council.
2606-52184 SPL
State Assessment and Referral Agency
Page 3 of 8
Confirmation of
relevant person
for proposed tidal works
Under s 123 of the
Coastal Protection and Management Act 1995,
it is necessary to ascertain
who will be the responsible party (relevant person) for the proposed works that are occurring on
State land. Specifically, a relevant person for the tidal works, and any person authorised by the
relevant person, has a right to occupy and use the State tidal land for each of the following –
a.
Carrying out the tidal works; and
b.
If the tidal works include the construction of a structure – maintaining the structure.
There may be impacts on coastal resources if no ownership of the tidal works is obtained, for
example,
section
124
of
the
Coastal
Protection
and
Management
Act
1995
states
that
the
relevant person must ensure that the structure is maintained in a safe condition. It is pertinent
that the relevant person is ascertained prior to obtaining an approval to ensure that the structure
is maintained post- construction.
It
is
recommended
that
the
applicant
confirm
who
the
relevant
person
is
under
s
124
of
the
Coastal Protection and Management Act 1995
prior to lodging a development application.
It is highlighted that the subject land is State coastal land and therefore, the relevant party to
apply for the development approval would ordinarily be Gladstone Regional Council unless the
applicant can demonstrate that they have been granted the necessary authority or consent to act
on behalf of the landowner or managing authority in relation to the proposed works. Evidence of
such authority should be provided to support the application.
The following additional advice outlines aspects that are relevant from the jurisdiction of SARA:
Table 2: Additional SARA advice
Clearing native vegetation
1.
A
review
of
the
submitted
information
illustrates
that
vegetation
clearing
for
the
development
may impact on the following vegetation categories:
Category X area
Category B area (Least concern and of concern regional ecosystems)
Proposed
vegetation
clearing
associated
with
the
development
within
the
road
reserve
(Flat
Rock Road) may be considered accepted development under Schedule 7, Part 3, Section 12 of
the Planning Regulation 2017 (Planning Regulation).
On this basis, the proposed clearing within the road reserve appears not assessable by SARA
as it may be undertaken under an Accepted Development Vegetation Clearing Code (ADVCC)
for
necessary environmental clearing
.
The code is available online, and a notification can be lodged with the Department of Natural
Resources
and
Mines,
Manufacturing
and
Regional
and
Rural
Development
through
the
Queensland Government website:
https://www.qld.gov.au/environment/land/management/vegetation/clearing-approvals/codes
Development within a declared Fish Habitat Area (FHA)
2.
Under the Planning Regulation, development within a declared FHA must be undertaken in
accordance with the relevant
accepted development requirements
(ADR) or under a
development approval (assessable development).
The proposed works are within the Baffle Creek declared FHA, management B area. Based
on the information provided it appears that the proposed works cannot meet relevant ADR
2606-52184 SPL
State Assessment and Referral Agency
Page 4 of 8
and therefore, a Resource Allocation Authority (RAA) and development approval is required
to undertake the proposed works within the declared FHA.
o
In an application for a development approval for operational works involving
development in a declared FHA, the following will need to be provided:
completed copy of DA Form 1
a full response to State Development Assessment Provisions (SDAP) State
Code 12: Development in a declared FHA
o
RAAs provide allocation of, or entitlement to, the resource to enable works to be
performed under a development approval, as required under section 76A of the
Fisheries Act 1994
. A RAA needs to be obtained from the Department of Primary
Industries prior to the commencement of development works.
It is recommended that a RAA is obtained prior to submission of a development
application as this will simplify addressing the SDAP for development in a declared
FHA.
Section 61 of the Fisheries (General) Regulation 2019 broadly outlines the
restrictions on issuing RAAs and the matters that must be taken into account when
deciding an application for a RAA:
an RAA may only be issued in a declared FHA for a prescribed development
purpose
regard must be had to the effect of the development proposal on
maintenance of community use, the natural condition of fish habitats and
current fish habitat values and functions. Refer to
Operational policy:
Management of declared Fish Habitat Areas
for further information.
As per section 61 of the Fisheries (General) Regulation 2019 and PO1 of the SDAP
State
Code 12: Development in a declared Fish Habitat Area
, development within a declared FHA
can only be undertaken for a prescribed development purpose as defined in section 60 of
the Fisheries (General) Regulation 2019.
The construction of a rock groyne and beach replenishment within a management B area
may be permissible under the prescribed development purposes
6.10 constructing a
permanent structure on tidal lands
, and
6.11 depositing material for beach replenishment for
the purpose of erosion control.
However, the proposed works would need to demonstrate
compliance with the requirements of the
Operational Policy: Management of declared Fish
Habitat Areas
, including specific policy interpretation (SPI) 12:
Revetments, groynes and
gabions
.
Additional works are mentioned within the material including permanent and temporary
access tracks. A temporary access track to facilitate the construction of the groyne and
beach replenishment may be permissible under the prescribed development purpose(s)
6.8
Constructing a temporary structure.
However, a permanent access track within the FHA is
unlikely to meet a prescribed development purpose as permanent access tracks do not have
an overriding physical requirement to be within an FHA (see section 6.10.2 of the FHA
policy).
Additional proposed works are also shown within Figure 1 (see Attachment 1 of this pre-
lodgement advice), including a road, additional rock armouring, a launching ramp / pontoon
and parking. Many of these aspects appear to be within the FHA. It is unlikely these will
meet a prescribed development purpose.
Based on the information provided, the source location of the sand has not been identified.
Under the
Operational Policy: Management of Declared Fish Habitat Areas (SPI 6: Dredging
or extracting sediment)
, dredging or sediment extraction within Management A or
Management B areas for the purpose of beach replenishment is unlikely to be supported,
due to the potential impacts on fisheries values and community use of the fish habitat area.
2606-52184 SPL
State Assessment and Referral Agency
Page 5 of 8
The
SDAP Guideline for
State Code 12
will assist in the preparation of a development
application and responding to the relevant Performance Outcomes (POs) for assessable
development impacting declared fish habitat areas.
In a development application it is recommended to:
o
Clarify what works are proposed within the declared FHA
o
Provide information on the source of sand for the replenishment works
o
Detail how any temporary work will be removed and the site returned to natural
conditions
o
Provide a site scaled plan showing:
The georeferenced location of all works within the FHA.
The extent, nature and dimensions of the area of the proposed work,
including but not limited to temporary access paths and refining the extent of
the rock groyne. As proposed, the rock groyne appears to form part of
additional rock armouring that has not been described within the material
provided
Location and extent of the HAT.
Mean high water springs and mean low water springs levels, by reference to
easily identifiable fixed points.
Real property boundaries adjacent to and in the vicinity of the proposed
work.
Impacts on marine plants
3.
The proposed works may result the removal, destruction or damage of marine plants. If the
works do impact on marine plants, they will be assessable development and require a
development approval.
Please refer to the webpage
marine plants
for further information.
If applicable, the
SDAP Guideline for State Code 11
(the Guideline) will assist in the preparation
of the development application and responding to the relevant Performance Outcomes (POs) for
assessable development impacting marine plants.
o
See section 2.1 to 2.1.4 of the Guideline: what constitutes a marine plant as per the
Fisheries Act 1994.
o
Section 4 of the Guideline: Standard information for all applications.
Should
you
require
further
information,
it
is
recommended
that
you
seek
additional
pre-
lodgement advice once you have further details of the nature of the proposal and any impact on
marine plants.
Operational work for tidal works
4.
Based on the information provided, the proposed rock groyne and beach nourishment will likely
trigger assessment for operational work for tidal works. Please note that if the beach
nourishment is above the high-water mark on State coastal land in the coastal management
district, the trigger would be operational work for interfering with quarry material.
Erosion control structures, such as groynes, can have significant adverse effects on coastal
processes. These structures may disrupt natural sediment transport pathways, resulting in the
accumulation of sand on the updrift side and reduced sediment supply to downstream areas.
Consequently, they can alter shoreline dynamics and potentially exacerbate coastal erosion at
adjacent properties. The applicant is therefore advised to review the Coastal Hazards Technical
Guide to better understand the potential impacts and considerations associated with such works:
Coastal Hazards Technical Guide.
It is recommended that soft erosion control structures be
considered.
Tidal work is defined in the
Coastal Protection and Management Act 1995
as:
2606-52184 SPL
State Assessment and Referral Agency
Page 6 of 8
Tidal works means any of the following—
a.
works in, on or above—
(i)
land under tidal water; or
(ii)land that will or may be under tidal water because of development on or
near the land;
b.
works that are—
(i)
an integral part of works mentioned in paragraph (a) (the principal works);
and
(ii)carried out in, on or above land directly adjacent to the land in, on or above
which the principal works are carried out;
c.
works designed to be exposed to tidal water because of shoreline fluctuations;
d.
works designed to prevent the erosion of land by the sea (whether or not within the
ebb and flow of the tide at spring tides);
e.
works within the boundaries of a canal, whether above or below high-water mark.
If you determine that the proposed works are tidal works, a response to SDAP State code 8 –
Coastal development and tidal works is required, identifying how the proposed development
meets each PO.
Rock groyne
The relevant POs for this proposed structure are:
o
Development in the erosion prone area – PO3 and PO4;
o
Coastal protection work – PO10 and PO12;
It is noted the picnic shelter and table would not be considered as a ‘significant
buildings or infrastructure’ under PO10.
o
Water Quality – PO13;
o
Public use of and access to State coastal land – PO14 and PO16; and
o
Matters of State Environmental Significance (MSES) – PO17.
Beach nourishment
The relevant POs for this proposed work are:
o
Coastal protection work – PO8 and PO9;
o
Water quality – PO13;
o
Public use of and access to State coastal land – PO14.
o
MSES – PO17.
MSES
Where relevant MSES are identified, provide a targeted assessment to verify extent,
demonstrate avoidance and minimisation of impacts to the greatest extent practicable, and
determine whether a significant residual impact will occur in accordance with the
Significant
Residual Impact Guideline
.
Wetland protection area
5.
Based on the information provided, it is unclear whether the proposed development (rock groyne
and beach nourishment works) will trigger assessment for high impact earthworks in a Wetland
Protection Area (WPA). It is recommended that you review the definition of ‘high impact
earthworks’ under the Planning Regulation.
Should the proposed development trigger assessment for high impact earthworks in a WPA, it is
recommended that a response addressing SDAP State Code 9: Great Barrier Reef wetland
protection areas be prepared and supported by relevant specialist reporting/ technical
investigations.
2606-52184 SPL
State Assessment and Referral Agency
Page 7 of 8
M
aritime safety (navigation corridor)
6.
Should the proposal trigger assessment for operational work that is tidal works or work within a
coastal management district in tidal waters under Schedule 10, Part 17, Division 3, Table 2, Item
1
of
the
Planning
Regulation,
you
will
need
to
demonstrate
compliance
with
State
Code
7:
Maritime safety of the SDAP. The following information would be required to be provided:
Clarify whether the proposed structure is a standalone rock groyne or part of a larger
coastal
protection
structure,
noting
the
submitted
plans
appear
to
show
a
more
extensive rock wall.
Provide GPS coordinates for the seaward and landward extents of the proposed groyne.
Demonstrate how navigational safety will be maintained during and after construction.
Demonstrate that any post-construction sand accretion will not adversely affect the safe
navigation of existing channels.
The
following
advice
is
provided
for
the
applicant’s
consideration,
which
is
outside
the
jurisdiction
of
SARA:
Table 3: Additional advice outside jurisdiction of SARA
Marine Parks
1.
As the development is located in a State marine park, a permit to undertake the activity may be
needed from DETSI Statewide Marine Works. Please see the following link for more information:
https://www.qld.gov.au/environment/coasts-waterways/marine-parks/permits
If
you
wish
to
enquire
about
obtaining
a
marine
park
permit,
please
contact
marineparksworks@detsi.qld.gov.au
.
This advice is provided in good faith and is:
based on the material and information provided to SARA
current at the time of issue
not applicable if the proposal is changed from that which formed the basis of this advice.
This advice does not constitute an approval or an endorsement that SARA supports the development
proposal.
Additional
information
may
be
required
to
allow
SARA
to
properly
assess
the
development
proposal when a formal application has been lodged.
If you require further information please contact Lydia Summers, Principal Planning Officer, on 07 5644
3217 or via email RockhamptonSARA@dsdip.qld.gov.au who will be pleased to assist.
Yours sincerely
Anthony Walsh
Manager Planning
2606-52184 SPL
State Assessment and Referral Agency
Page 8 of 8
Attachment 1- Proposal within fish habitat area (FHA)
Figure 1: Proposal plan - groyne and beach replenishment within the FHA
📤 SENT – To: mark francis GRC
📅 August 21, 2026

Re: Fw: Flat Rock - 2015 master plan

Summary: You'll forgive me, but it has been a month with no response.

📄 Click to view full letter
hi again Mark, You'll forgive me, but it has been a month with no response. Thank you for your letter. To be honest, apart from Natalia, we have received very little positivity from GRC regarding anything to do with Flat Rock. This stands in stark contrast to when the plan was first put together. Tony Klein, the then-Manager of Parks and Environment, was a great collaborator—I would speak to him every few days at that time. Once he left, I don't recall anyone from GRC reaching out to us at all, except for councillors like Natalia and Rick. I believe the construction of the boat ramp suffered immensely as a result of the community not being involved. I understand the Baffle community can be difficult, but I am not. And I understand you are human too—but we need at least a conversation. You mentioned in your letter that Council intends to engage with the community to understand local aspirations. With respect, we have been waiting for that engagement since 2015. In all that time, not one idea or vision has been presented to us, despite our repeated advocacy. Baffle Creek currently has the worst playground and facilities in the entire region. We don't need another master plan—we need a conversation. I'm asking you directly: can we please talk? i think informally by phone would be a great start (0416270831) Sunirmalya Symons Baffle Creek Boat Club e: sunirmalya@bafflecreekboatclub.org.au | w: bafflecreekboatclub.org.au
📥 RECEIVED – From: Pauline Jacob Deputy Director-General Fisheries and Forestry
📅 July 24, 2026
✓ Responded

Decision – Application for fee waiver under the Fisheries Act 1994 and the Fisheries (General) Regulation 2019 for a Resource Allocation Authority to interfere with a declared Fish Habitat Area (FHA).

📄 Click to view full letter
Microsoft Word - 12259-26_2648850_DPI_DDG_FF_Letter




Our ref: CTS 12259/26










Mr Sunirmalya Symons sunirmalya@bafflecreekboatclub.org.au

Department of

Primary Industries


Dear Mr Symons


Thank you for your email of 25 June 2026 regarding a fee waiver request for a resource allocation authority application for works at the Flat Rock Picnic Area, Baffle Creek. I have approved the waiver of the prescribed application fees for the application.

Decision – Application for fee waiver under the Fisheries Act 1994 and the Fisheries (General) Regulation 2019 for a Resource Allocation Authority to interfere with a declared Fish Habitat Area (FHA).

Proposal: Construction of a 7m x 2m rock groyne with associated beach replenishment

Location: Baffle Creek declared Fish Habitat Areas, management B area

Property Description: Flat Rock Picnic Area, Baffle Creek


I have considered your request under section 143 of the Fisheries (General) Regulation 2019 and the relevant matters outlined in the DPI Fee Guideline. In making my decision, I have given regard to the extent to which the activity being authorised is associated with government policies and initiatives. Specifically, I note that:

  • the Baffle Creek Boat Club is a not-for-profit community organisation

  • the Queensland Government has previously provided funds to the club for active girls to participate in sport and recreation activities

  • the works are to protect and enhance public infrastructure

  • the works will facilitate public access to the declared FHA


Having regard to these factors, I am satisfied that the application delivers broader public and sector-wide benefits and helps maintain access and use of the declared FHA. This supports the approval of the fee waiver under my delegated authority from the Chief Executive.






Level 12, 275 George Street

Brisbane QLD 4000 GPO Box 46 Brisbane Queensland 4001 Australia

Business Centre 13 25 23 Website www.dpi.qld.gov.au ABN 66 934 348 189

If you require any further information, please contact Richard Stewart, Fisheries Queensland on 07 5381 1360 or by email at planningassessment@dpi.qld.gov.au.

Yours sincerely



Pauline Jacob

Deputy Director-General Fisheries and Forestry






























































Department of Primary Industries Page 2 of 2

📤 SENT – To: Mark Francis
📅 July 22, 2026

what happened to the 2015 master plan

Summary: what happened to the 2015 master plan

📄 Click to view full letter
hi Mark, Thank you for your response and for taking the time to outline Council's current position regarding the Flat Rock Master Plan. I appreciate the clarification that the 2015 Master Plan was intended as an aspirational planning document rather than a commitment to deliver all proposed projects. I also acknowledge that community needs and priorities do evolve over time, and that Council intends to engage with the community to better understand local aspirations. However, I must be candid with you about the situation from our perspective. It has now been 11 years since the Master Plan was developed, and very little of its vision has been realised at Flat Rock. The community is understandably skeptical that meaningful improvements will eventuate without a more structured and timely commitment. The Baffle Creek Boat Club has been actively pursuing solutions to address the ongoing erosion at Flat Rock Picnic Area, which threatens public infrastructure including the boat ramp and picnic facilities. As you may be aware, we are currently preparing applications for a Resource Allocation Authority and a development application through the State Assessment and Referral Agency (SARA) for beach replenishment and erosion control works. These works are essential to protect public assets and maintain safe access to Baffle Creek. Our concern is that "future engagement" without a defined timeline risks becoming an indefinite deferral. We are keen to work collaboratively with Council to progress improvements at Flat Rock, but we need clarity on how and when this will happen. I therefore respectfully request the following: An indication of when the intended community engagement is likely to occur – even a broad timeframe (e.g., within the next month or two) would be helpful for our planning Clarification on how the Club can best contribute to this process – we are keen to be proactive partners in shaping the future of Flat Rock. Consideration of whether Council would support the Club's current erosion control application – as this aligns with the Master Plan's objectives and would protect public infrastructure without requiring immediate Council funding. The Baffle Creek Boat Club remains committed to advocating for the Baffle community. We look forward to working with Council to ensure that the aspirations of the 2015 Master Plan – and the needs of the broader community – are ultimately realised. I would welcome the opportunity to discuss this further at your convenience. Kind regards, Sunirmalya Symons Secretary Baffle Creek Boat Club Email: sunirmalya@bafflecreekboatclub.org.au
📥 RECEIVED – From: Mark Francis GRC
📅 July 22, 2026
✓ Responded

what happened to the 2015 master plan

Summary: what happened to the 2015 master plan

📄 Click to view full letter
On Thu, 23 Jul 2026 at 09:44, Mark Francis wrote: Hi Suni, Thank you for your email and for your ongoing interest in the future of Flat Rock. The 2015 master plan was developed to explore opportunities for the area and provide a long-term vision for how Flat Rock could evolve over time. As with most master plans, it was intended as a planning document to identify potential improvements and aspirations rather than a commitment by Council to deliver all projects shown within the plan. Council recognises that community needs and priorities change over time. As part of our future planning, we are intending to engage with the wider community and key stakeholders to better understand local aspirations and priorities for development. This work will help inform local plans that can guide future investment in community infrastructure and public facilities across the region. The timing and approach for this engagement are yet to be determined and will ultimately be considered by Councillors as part of Council's broader planning and engagement program. We appreciate your advocacy for Flat Rock and the interest shown by the Baffle Creek Boat Club. Your views, along with those of the broader community, will be valuable when future engagement opportunities arise. Gladstone Regional Council Mark Francis General Manager Assets and Environment Assets and Environment PO Box 29 Gladstone Qld 4680 P (07) 4970 0700 | M 0419 153 641 W www.gladstone.qld.gov.au
📤 SENT – To: planningassessment@daf.qld.gov.au
📅 July 6, 2026

Resource Allocation Authority Flat Rock Picnic Area - Baffle Creek 25 June 2026

Summary: This is the Resource Allocation Authority application for the Flat Rock Picnic Area - Baffle Creek that goes to State Govt for the groyne and beach replenshment

📄 Click to view full letter

Dear Fisheries Queensland,

Application for Resource Allocation Authority for Works in a Declared Fish Habitat Area

The Baffle Creek Boat Club (the Club) hereby submits this application for a Resource Allocation Authority (RAA) under the Fisheries Act 1994. The application is for operational works to be carried out at the Flat Rock Picnic Area, Baffle Creek, within the Baffle Creek declared Fish Habitat Area (FHA-031) .

1. Applicant Details

Item

Details

Applicant

Baffle Creek Boat Club

Contact Person

Sunirmalya Symons, Secretary 

Postal Address

C/- 731 Pacific Drive, Deepwater QLD 4674 

Street Address of Works

Flat Rock Road, Rules Beach QLD 4674 

2. Project Overview

Item

Details

Location

Flat Rock Picnic Area, Baffle Creek, QLD 4674 

Local Government Area

Gladstone Regional Council 

FHA Plan Number

FHA-031 (Revision 1) 

FHA Management Zone

The application site is within the Management B zone of the FHA, following the 2024 re-declaration .

Proposed Works

Construction of a 7m x 2m rock groyne with associated beach replenishment to address ongoing coastal erosion threatening public infrastructure .

3. Environmental and Regulatory Context

The 2024 re-declaration of the Baffle Creek FHA (FHA-031, Revision 1) specifically excluded the area within 30 metres of the public boat ramp at Flat Rock Road from the FHA . The Club's proposed works are located adjacent to this excluded area within the Management B zone .

The resource allocation authority is required as the proposed operational works are within a declared fish habitat area . The proposed activities constitute operational works impacting on tidal land and requiring assessment against the fisheries resources of the area .

4. Supporting Documentation

Enclosed with this application are:

  1. Completed Resource Allocation Authority application form with 2 attached pdf files providing requested details

  2. Site plans showing the proposed works footprint and disturbance areas

The Club is available to provide any additional information required to support this application. Please direct any correspondence to the contact details provided above.

Yours sincerely,

Sunirmalya Symons

Secretary
Baffle Creek Boat Club
sunirmalya@bafflecreekboatclub.org.au




RAA application RAA attachment 1.pdf RAA attachment 2.pdf Map baffle-creek-fha-031.pdf
📥 RECEIVED – From: Stephen Bennett
📅 June 3, 2026

Fix Flat Rock

Summary: Fees reduced

📄 Click to view full letter

Re: RAA and SARA Fee 1 message


Burnett Electorate Office 4 June 2026 at 08:35 To: sunirmalya symons


Hi Suni,





Member for Burnett, Stephen Bennett, has advocated on the Club’s behalf with the relevant Ministers and Departments to reduce approval c osts for the sand replenishment project.


Stephen understands that even with these reductions, the remaining costs are still significant for the Club, however, they are a substantial r eduction from the original figures and were achieved following considerable engagement with the relevant agencies.


Reduction of the Resource Allocation Authority (RAA) fee

A resource allocation authority is required for this sand replenishment project under the Fisheries (General) Regulation 2019 (the Regulation) as the proposed works will be within the Baffle Creek declared Fish Habitat Area. A resource allocation authority is a requirement for any development work to be carried out with a declared Fish HabitatArea and there is no scope to remove this requirement for this project.


The fees associated with making a resource allocation authority application are outlined in Schedule 5 of the Regulation. Under Section 143 o f the Regulation, the Chief Executive or delegate may waive or refund a fee stated in Schedule 5.


The Baffle Creek Boat Club can make a request to the Deputy Director-General, Fisheries and Forestry to have the fees waived when s ubmitting the application for a resource allocation authority. The Club will be advised of the outcome of any request for a feewaiver prior to t he assessment of the application for a resource allocation authority.


Reduction of the State Assessment and Referral Agency fee

Under Schedule 10 of the Planning Regulation 2017 (the Planning Regulation), SARA’s full prescribed fee for assessing an application for w ork in a declared fish habitat area and tidal works is $9,397.


The Planning Regulation allows for a 50 per cent reduction of the prescribed SARA fee at the time of lodgement for applicants who are r egistered not-for-profit organisations. The Baffle Creek Boat Club qualifies for this fee reduction. This will reduce theSARA application fee, to b e paid at lodgement, to $4,698.50.


SARA can also consider requests for full or partial refunds of application fees after the application has been lodged or referred and the p rescribed fees have been paid. As the project involves sand nourishment of a beach for public safety purposes, SARA wouldlikely support a r equest for a 50 per cent refund of the prescribed fee ($4,698.50), further reducing the fee for the assessment of the application by SARA to $ 2,349.25.


Please see the below table summarising the potential reduction in costs Stephen has secured for the Baffle Creek Boat Club: Full Fee Reduction/ outcome

Resource Allocation Authority ( RAA)

State Assessment and Referral A gency (SARA)

$3,985.71 (30-year approval) The Baffle Creek Boat Club can request for the Resource A

llocation Fee to be waived.

$9,397 The Planning Regulation allows for a 50 per cent reduction of the p rescribed SARA fee at the time of lodgement for applicants who a re registered not-for-profit organisation, reducing the Club’s SARA a pplication fee, to be paid at lodgement, to $4,698.50. Inaddition, S ARA would likely support a request for a 50 per cent refund of the f ee, further reducing the SARA fees to $2,349.25.

Textbox 1

Kind Regards,

Textbox 2

Tyler Poole


📤 SENT – To: Stephen Bennett
📅 May 9, 2026

Fix Flat Rock meeting request

📄 Click to view full letter

Dear Stephen,

Thank you for everything you do for the local community.

Our public meeting to Fix Flat Rock was well attended by a positive and engaged community, along with Acting Mayor Natalia Muzskat. The purpose of the meeting was to identify community priorities and develop a practical path forward for restoring Flat Rock.

After careful discussion, the community has decided that the Fix Flat Rock team will operate separately from the Boat Club. This will allow us to:

  • Be more flexible in responding to the entire community's priorities

  • Engage a wider range of stakeholders (residents, businesses, visitors)

  • Work collaboratively with both Council and State Government without being limited by a single organisation's capacity


Community Priorities Identified at the Meeting

Sand and a Groin

The top priority is installing sand and a groin to help restrict currents and reduce the ongoing loss of sand at Flat Rock.

It was recognised that this may need to be separated into two distinct tasks to reduce completion time and complexity.

We want to acknowledge and thank you for your hard work in reducing the SARA and RAA fees. As you know, however, the full scope of work required is beyond the capacity of the Boat Club to finance on its own.

Our hope is that we can engage Council and your government to work out the details, whilst allowing the Boat Club to implement ongoing sand maintenance. This would leverage our local knowledge and decades of experience, whilst also helping the Boat Club financially.

You would be aware that this sand replenishment has been the Boat Club's responsibility for over 40 years.


Request for a Meeting

If you believe it would be helpful, I am hoping that you may be able to arrange a meeting with your appropriate department's responsible staff.

I will work on inviting GRC Deputy Mayor Muzskat and her relevant staff. Ideally, this could be:

  • At GRC offices

  • Onsite at Flat Rock

  • Via Zoom (or whatever you suggest)

I will attend, along with one or two members of our steering committee.

The agenda would be simply to identify as quickly as possible how to proceed for each of the attendees.


Next Steps

We remain committed to working constructively with you and your office. Our steering committee is now forming, and we look forward to your advice on how best to move forward. Other priorities were also identified but related more specifically to GRC.

Thank you again for your ongoing support of Baffle Creek.

Warm regards,

Sunirmalya (Sunny) Symons
On behalf of the Fix Flat Rock Steering Committee

📧 fixflatrock@enviro.org.au
📞 (07) 4186 9237
🌐 
fixflatrock.dreamhosters.com



Have something to add?

Email us your suggestions, or if you have a direct response to share with the community.